CNC Drawing Revision Control After the Order Is Placed

In this guide

When a CNC drawing changes after an order is placed, send a controlled change package and obtain the supplier’s written response before assuming the new revision is in production. Identify the affected order, explain the change and agree what happens to work already started. Replacing a file in a shared folder does not establish those decisions.

This guide addresses the handover between engineering, purchasing and your CNC machining services supplier. For the original quotation package, use the CNC quote requirements guide. Here, the question is how to introduce a revision while keeping the order and existing parts traceable.

Key Takeaways

  • Name the affected part, purchase order, old revision and new revision in one change notice.
  • Ask for the production status and quantities already committed before agreeing the changeover.
  • Release matching CAD, drawing and inspection requirements together.
  • Keep old-revision stock identifiable until its disposition is agreed.

Establish Which Work Is Affected

AI-generated illustration of a machined aluminum plate beside plain document folders

Start with the order line, part number and current revision. State whether the request applies to the whole open order, the next lot or future orders only. If affected work must pause, make that request explicit and ask the supplier to confirm what has been held.

Request a dated status report with quantities at each stage: material allocated, machining started, finishing in progress, finished stock and shipped parts. Do not assume that a delivery date in the future means no work has begun. Use the report to identify where the proposed change needs a decision.

The distinction between a file update and an order change also appears in Xometry’s revision guidance: applying a new revision to an existing order requires contact with its team and depends on production status. Agree the corresponding communication route with your own supplier.

Send the Difference and the Complete Requirements

Provide a concise change summary alongside the complete revised files. A marked comparison helps the supplier find the change; it should not be the only source of manufacturing requirements.

For example, if a mounting hole moves, identify the affected feature and its relationship to the mating component. If only a note changes, identify that note and explain whether it changes acceptance. A finish note can matter even when the solid model looks identical.

Ask the supplier to review the effect on machining plans and inspection. Drawing geometry, dimensions and tolerance requirements inform CNC planning, so the review should cover the revised requirements rather than relying on the description “minor change.” Leave decisions about programming and workholding to the supplier’s manufacturing review.

Change-package item What to include
Identity Part number, order line and old/new revision identifiers
Released files Complete current drawing, model and referenced specifications
Change summary Affected features or notes and the reason for the change
Effective scope Orders, lots or quantities to which the change should apply
Acceptance Changed inspection, functional or appearance requirements
Open decisions Work in progress, old stock, cost, schedule and approval responsibility

Where documents disagree, resolve the discrepancy with the design authority before release. State the governing-document rule agreed for the order, but do not use that rule as a substitute for correcting a known conflict. Retain superseded files in the history while making the current production package unambiguous.

Decide What Happens to Existing Parts

List old-revision quantities separately from new-revision quantities. For each affected group, record whether it is held for review, accepted for an identified use, proposed for rework or rejected. These are decisions for the authorized buyer and technical team, with the supplier’s feasibility input.

Do not relabel an old part as the new revision merely because it looks similar. If engineering determines that existing parts meet the revised requirements, record the basis and applicable quantities. If rework is proposed, agree the rework scope and how the resulting parts will be inspected before release.

Consider stock already shipped as well as stock at the supplier. A controlled changeover is incomplete if purchasing switches future orders while assembly continues using unidentified old stock. Agree how the receiving and assembly teams will distinguish the lots that matter to the change.

Obtain an Acknowledged Changeover Record

Before resuming affected work, collect the supplier’s response on scope, feasibility, price and delivery impact. Separate acknowledgment of receipt from acceptance of the requested change. “Files received” does not answer whether the current order can be changed.

Record the first order, lot or quantity that will use the new revision. Agree what inspection evidence is needed for the changed features and any affected interfaces. The CNC inspection requirements guide can help define that evidence without inventing a universal sample size.

Close the notice only when the released files, order instructions, supplier acknowledgment and old-stock disposition agree. Keep unresolved questions visible, with an owner and a next action. That gives the next buyer or engineer a usable record when the part is reordered.

Reconcile Mixed Revisions at Receiving

When the changeover permits delivery of more than one revision, agree the receiving record before shipment. Keep each revision’s quantity, lot identity and inspection evidence distinguishable. A delivery note that lists only the combined part quantity leaves the receiving team without the information needed to apply the change decision.

Use separate lines for each revision and disposition. For illustration, an open order for 100 brackets might be fulfilled with 30 Rev B parts and 70 Rev C parts only if the authorized team has approved that split. The record should identify the approved use of the 30 Rev B parts; the quantity total alone does not authorize their use.

Receiving check What to reconcile
Order instruction Permitted revision and quantity on each order line or approved change notice
Pack identification Part number, actual revision, lot and quantity for each identified pack
Inspection evidence Report identity and revision applicable to the parts it covers
Old-revision disposition Written decision and any restrictions on where the parts may be used
Receipt outcome Quantity accepted, held or discrepant, with a named owner for unresolved items

Ask the supplier to reference the change notice on the dispatch documents. Pass the same notice to receiving and assembly, including restrictions on old stock. If the pack label says Rev C but its report refers to Rev B, hold the affected parts for reconciliation rather than choosing whichever document appears newer.

Do not replace the actual part revision on a label with the revision of the order simply to make the paperwork agree. If an authorized review finds old parts acceptable for a particular use, preserve their identity and link the disposition. If reworked parts are released to the new revision, retain the rework and inspection evidence that supports that decision.

Close the changeover by comparing the supplier’s shipped quantities with your receipt and remaining-stock records. Record unresolved shortages or mismatches separately. This extends the engineering change through delivery, so a later reorder does not inherit an unexplained mixture of revisions.

Keep Temporary Deviations Out of the Next Reorder

A supplier may propose a limited departure from the released drawing without asking you to change the permanent design. Treat that as a separate decision with a defined scope. Xometry’s guidance on drawing requirements outside process limits describes agreeing deviations and recording them for manufacturing and inspection. Your own order needs an equally clear record of what was accepted.

Before authorizing a temporary deviation, ask the design authority to identify the affected feature, the proposed requirement and the evidence needed to judge fit or function. Purchasing should then connect that decision to the exact order and quantity. Approval to investigate a proposal is not approval to manufacture or ship it.

Deviation field Decision to record
Baseline Part number, released drawing revision and affected feature or note
Permitted departure Exact alternative requirement and any conditions of use
Scope Named order lines, lots and maximum quantity covered
Evidence Inspection or functional checks required before release
End point Expiry date, quantity limit or event that closes the authorization
Authority Named approver and the written decision reference

For example, an approval covering 20 trial brackets on one order should not be copied into a repeat order for 200 brackets. Those quantities are illustrative. Keep the drawing revision on the part record and attach the deviation reference to the affected lot; don’t give the exception the appearance of a newly released design.

At reorder, check whether the deviation has expired or its quantity has been consumed. If the alternative is intended to become permanent, route it through the drawing-change process and release matching files. If it remains temporary, obtain a fresh scoped decision before the supplier relies on it. This gives receiving a clear basis for accepting one identified lot while retaining the original requirements for subsequent work.

Frequently Asked Questions

Can I email a revised STEP file and keep the old PDF?

Only release a package whose documents consistently describe the agreed requirements. If the PDF is still valid, establish that explicitly under your document-control procedure. If it conflicts with the new model, correct it before production relies on the revised package.

Does a drawing change always require a new quote?

Ask the supplier to assess the effect on the open order. A change may alter scope, committed work or delivery, but the outcome is project-specific. Record any confirmed commercial change, including a response that the original terms remain applicable.

Can old-revision parts still be used?

That depends on the change and the authorized engineering decision. Identify the parts and their intended use, review whether they meet the applicable requirements, and document the disposition. Do not assume interchangeability from appearance or from the size of the revision note.

Request a DFM Review

Changing a CNC part before its next production run? Send the current and proposed drawings, matching models, change summary and affected order quantities. Identify the mating features and acceptance requirements that drove the revision.

Request a DFM review to discuss the manufacturing implications before releasing the changed work.